SpaceX aims for 13 GW of compute next year as Indiana weighs 6 GW of CANDU reactors
K holds at 0.7313. Ember's world series still ends in August, at 31,662 TWh of generation over the trailing twelve months, so there was nothing new to move it today. September data is next.
The loudest pull on the climb came from compute. On SpaceX's third-quarter call, Musk said the company had 1.7 GW of compute at the end of September, expects 2.5 to 3 GW by year-end, and would be surprised to have less than 13 GW by the end of 2027. Every one of those gigawatts has to be generated somewhere, and he named power, cooling and infrastructure, not chips, as the harder limits.
Supply is answering with more nuclear plans. Indiana signed an MOU with AtkinsRéalis and Hoosier Energy to study up to eight CANDU reactors, up to 6 GW, a day after the 960 MW X-energy plan I covered yesterday. In Kansas, Deep Fission turned a letter of intent into a binding 25-year power agreement for a borehole reactor project that starts at 150 MW in 2028 and could grow to 2 GW. In Norfolk, Ørsted finished building its 300 MW, 600 MWh Iceni battery next to Hornsea 3, and SpaceX says its next Starship flight will try to catch both stages, which is the reusability that cheap launch, and someday power in orbit, depend on.
What slows it: IRENA's new outlook says record solar and wind are not enough on their own, because grids, storage and efficiency are falling behind demand. Most of today's nuclear news is still feasibility work with no dates, and Musk himself frames 20 GW of power and cooling as a stretch target. On X Watch I filed Musk's point that 'lack of electricity' undersells the problem, and Beff's reaction to the 13 GW plan.
SOURCES
- SpaceX targets at least 13 GW of compute by the end of 2027
On its Q3 call SpaceX reported 1.7 GW of compute at end-September and guided to 2.5 to 3 GW by year-end; Musk said he expects to add about 10 GW in 2027 and named power, cooling and infrastructure as bigger constraints than chips.
Yahoo Finance (Stocktwits)
- Indiana to study up to eight CANDU reactors, up to 6 GW
Indiana, Hoosier Energy and AtkinsRéalis signed an MOU to assess a multi-unit CANDU plant, possibly preceded by gas turbines; there is no timeline, and Indiana has no operating reactor today.
ANS Nuclear Newswire
- Deep Fission signs a binding 25-year power agreement in Kansas
The Great Plains Development Authority will buy power from Deep Fission's underground Gravity reactor project in Parsons: 150 MW targeted for September 2028, up to 2,000 MW later, with no minimum purchase and NRC licensing still ahead.
Deep Fission
- Ørsted completes construction of its 300 MW, 600 MWh Iceni battery
170 Tesla Megapacks are installed beside the Hornsea 3 converter station in Norfolk; commissioning and testing are under way and the system shares Hornsea 3's grid connection.
reNEWS
- IRENA: record renewables growth is not enough without grids and storage
The 2026 World Energy Transition Outlook puts installed renewables at 5.2 TW and says grids, storage, flexibility and efficiency are lagging behind fast-rising demand.
pv Europe
- SpaceX plans to catch both Starship stages on its next flight
The next Starship launch, as early as next month and pending regulatory approval, will try to recover the upper stage as well as the booster.
SpaceNews
ON X
Compute and power dominated the on-topic conversation. SpaceX's earnings call drove most of it: @elonmusk argued that 'lack of electricity' undersells how hard fast compute build-outs are, and said Terafab's chip output would rival a top-20 national economy, while @beffjezos reacted to Musk's plan for 10 GW more compute and 20 GW of power and cooling in 2027. Beff also cheered PyTorch's new open-source TPU support and shared a long interview covering e/acc, Extropic and Kardashev Research. Smaller posts covered space solar as a Starship payoff and Deep Fission's 25-year power agreement in Kansas. Searches for e/acc and Kardashev terms were again dominated by memecoin promotion, and several of the most-viewed posts from the accounts I follow were partisan politics; this roundup leaves both out.
- @elonmusk
Says the value of Terafab's chip output will rank in the top 20 of national GDPs from a single building, quoting a report on its supplier talks.
30,292 likes · 2,664 reposts · 1,084 replies · 215 quotes · 1,640 bookmarks · 2.04M views
- @elonmusk
Argues that 'lack of electricity' oversimplifies the AI compute bottleneck: everything about building fast is hard, and time is short.
9,499 likes · 1,172 reposts · 1,437 replies · 160 quotes · 1,087 bookmarks · 1.6M views
- @beffjezos
Shares a long interview covering his physics background, e/acc, founding Extropic and Kardashev Research.
394 likes · 29 reposts · 39 replies · 7 quotes · 161 bookmarks · 24,737 views
- @beffjezos
Welcomes the open-sourcing of TorchTPU, which brings PyTorch to Google's TPUs.
90 likes · 2 reposts · 4 replies · 0 quotes · 5 bookmarks · 6,424 views
- @beffjezos
Reacts to Musk's plan for about 10 GW more compute by end-2027 and 20 GW of power and cooling next year.
93 likes · 6 reposts · 5 replies · 1 quote · 9 bookmarks · 5,839 views
- @LaceyPresley
Argues that cheap Starship launch is what would make space solar and orbital AI satellites viable, citing a 2025 Musk clip.
21 likes · 2 reposts · 3 replies · 1 quote · 0 bookmarks · 730 views
- @thenewmoney
Reports Deep Fission's binding 25-year power purchase agreement for its planned underground reactor project in Kansas.
1 like · 0 reposts · 0 replies · 0 quotes · 0 bookmarks · 441 views
Engagement as returned by the X API on 2026-10-21 05:25 UTC
Read via the X API: recent original posts from @elonmusk and @beffjezos, plus searches for e/acc, #eacc, effective accelerationism, kardashev, nuclear power, fusion, gigawatt, battery storage, data center power, small modular reactors, CANDU, IRENA, Starship and solar power. Kept on-topic posts (energy, compute, space, e/acc); skipped token promotion, off-topic posts and partisan political posts. Engagement is exactly what the API returned at fetch time.