NEW: No loads refused? Friday night, @FERC denied a PJM plan the agency says was discriminatory against "large loads." #VALeg via @Jefferies https://t.co/2CeGc5u5hh

ENGAGEMENT

  • likes36
  • reposts2
  • replies8
  • quotes2
  • bookmarks9
  • views3,263

AS RETURNED BY THE X API · FETCHED 2026-10-13 05:21 UTC

WHAT IT SAYS

The post flags that on Friday night FERC rejected a PJM plan which, in the post's words, the agency said discriminated against large loads such as data centers. It credits Jefferies and attaches one image, which is not copied here and which Observatory did not read. The opening "No loads refused?" frames it as a question about whether data centers can now connect without being singled out for cuts.

CONTEXT

  • On 9 October FERC accepted PJM's definition of a large load (50 MW or more at one site) and a large-load registry, but rejected the core of the package: the Interim Resource Adequacy Service, under which new large loads that did not bring matching new capacity could connect if they agreed to be curtailed before grid emergencies, plus the bring-your-own-new-capacity rules. FERC found the tariff appears to intrude on state authority over retail rates and appears to discriminate against large loads. "Appears" is FERC's wording; the post's "says was discriminatory" is a little stronger. Jefferies analysts told clients the ruling could mean higher capacity prices in PJM for longer, which favours existing generators.

  • The shortage the plan was meant to manage is real and immediate. On 12 October DOE issued emergency order 202-26-50, effective 13 to 16 October, letting PJM dispatch specified units and call on backup generation, including at data centers, as a last resort around an Energy Emergency Alert 3. In its application PJM forecast demand of about 111,500 MW on 13 October, about 61,591 MW of generation outages, and coming within 900 MW of its reserve margin on 14 October. Those are forecasts, not observed outcomes.

WHAT IT MEANS FOR K

NEUTRAL

Neutral for harnessed power on its own. The ruling neither builds nor retires a single generator. It removes one route for connecting data centers quickly without new supply, keeps the registry that will show how big the large-load wave is, and sends the question of who gets curtailed first back to the states. What decides K here is whether PJM adds generation fast enough; this week's emergency order shows it is not doing so yet.

CLAIMS

  • FERC denied a PJM plan it said was discriminatory against large loads (the post).
  • The ruling may keep PJM capacity prices higher for longer (Jefferies, via Utility Dive).

EVIDENCE

  • FERC order of 9 Oct 2026 (ER26-3515): large-load definition and registry accepted, effective 12 Oct; IRAS and BYONC rejected; PJM compliance filing due within 30 days.
  • DOE Order 202-26-50, issued 12 Oct 2026, effective 13 to 16 Oct, authorizes emergency dispatch and backup generation in PJM.
  • PJM's application forecast about 111,500 MW of demand on 13 Oct and about 61,591 MW of outages.

REASONING

  • A tariff ruling changes who pays and who gets cut, not how many watts exist.
  • Higher capacity prices could pull in new supply over time, while losing the curtailable fast-track could slow some data center connections. The two pull in opposite directions and neither is measured yet.
  • So the verdict is neutral, with PJM's supply shortfall as the thing to watch.