THE POST
Holy mother of compute mogging... 😳 https://t.co/Rtg4cMQBQn
QUOTED
Sawyer Merritt@SawyerMerritt
Elon: "I've been personally spending a lot of time in Memphis, often 4 days a week. We're tracking to bring 200,000 Nvidia GB200s online per month for the remainder of the year, and continuing that pace next year. I'm fairly confident to bring online an incremental 10 GW of compute by the end of 2027. We're also going to aim to bring online an incremental 20GW of power & cooling next year."
https://x.com/SawyerMerritt/status/2112647057014211028The quoted post carries one photo, which is not copied here. It says 'GB200s'; the reports of the call that Observatory opened say GB300s.
ENGAGEMENT
- likes93
- reposts6
- replies5
- quote1
- bookmarks9
- views5,839
AS RETURNED BY THE X API · FETCHED 2026-10-21 05:25 UTC
WHAT IT SAYS
Beff reacts with amazement to a quote from Elon Musk. In it Musk says he spends up to four days a week in Memphis, that SpaceX is bringing about 200,000 Nvidia GPUs online per month for the rest of the year and will keep that pace next year, that he is fairly confident of adding 10 GW of compute by the end of 2027, and that SpaceX will aim to add 20 GW of power and cooling next year.
CONTEXT
The quote comes from SpaceX's Q3 2026 earnings call on 20 October. Reports of the call put SpaceX's compute at 1.7 GW at end-September, up from 1.4 GW in Q2, with 2.5 to 3 GW expected by year-end. Musk said he would be surprised to have less than 13 GW of compute by the end of 2027, above ARK's forecast of slightly under 8 GW. The reports describe the monthly GPU installs as GB300s, not GB200s as the quoted post says, moving to Vera Rubin next year. SpaceX spent $19.6 billion on capex in Q3 and guided to $35 to 40 billion in Q4.
Musk has framed the 20 GW power-and-cooling figure as a target portfolio rather than a forecast. On the Q2 call he said he did not expect to reach 20 GW and that, if about a quarter of projects slip, close to 15 GW was more likely by the end of 2027. SpaceX plans to build more power and cooling than it has GPUs for, because the chips cost far more than the rest of the site.
For scale: BlockWest's tracker counted 4.1 GW of IT power running across the eleven largest US AI campuses in early October, with SpaceX/xAI's Colossus 2 at 946 MW of a planned 1,531 MW and running on gas turbines with on-site batteries.
WHAT IT MEANS FOR K
If even the 15 GW base case arrives, one company would add many gigawatts of power-and-cooling capacity within about 15 months, and every watt of it has to be generated somewhere. That is a direct pull on harnessed power. But it is a target stated on an earnings call, and SpaceX added about 0.3 GW of compute last quarter.
CLAIMS
- SpaceX is bringing about 200,000 Nvidia GPUs online per month for the rest of 2026 and will keep that pace in 2027.
- SpaceX will add about 10 GW of compute by the end of 2027.
- SpaceX aims to add 20 GW of power and cooling in 2027.
EVIDENCE
- Yahoo Finance (Stocktwits): 1.7 GW of compute at end-September, 2.5 to 3 GW expected by end-2026; $19.6 billion of Q3 capex.
- Crypto Briefing: capacity rose from 1.4 GW in Q2 to 1.7 GW in Q3.
- New Project Media: Musk called 20 GW a portfolio target and put his base case near 15 GW.
REASONING
- The direction is credible: capacity is rising every quarter and capex is large and growing.
- The size is not yet evidenced. By Observatory arithmetic, 13 GW at end-2027 is about 7.6 times the 1.7 GW of end-September, and adding 10 GW in a year means about 2.5 GW a quarter against roughly 0.3 GW in Q3.
- Large stated plans without delivery evidence at that scale are speculative under this site's rules.
SEE ON THIS SITE
TAGS
- COMPUTE
- DATA CENTRES
- POWER
- SPACEX
- GIGAWATTS