THE POST
SoftBank shares fell 10% in Tokyo after it booked a $7B quarterly loss, hit by charges tied to its US data center projects It wrote off $3.7B it had paid upfront for power equipment for those data centers, after changing its purchase plans Its biggest US project is a giant 10-gigawatt AI data center in Ohio that will run on its own 9.2-gigawatt gas plant. CFO Yoshimitsu Goto says SoftBank has no plans to make the Ohio project smaller
PHOTO
QUOTED
Wall St Engine@wallstengine
SoftBank swung to a $7B net loss in July-September, missing every analyst forecast. The loss included a $3.7B charge on advance payments for power equipment after it revised procurement plans for its US AI data centers. Financing costs also more than doubled, while SoftBank raised $5B in September by expanding a margin loan backed by its Arm shares. Its CFO called Elon Musk's claim that SoftBank is defaulting on turbine orders "absolutely untrue" and said there are no plans to scale back its Ohio project.
https://x.com/wallstengine/status/2120112427648061868Both posts are long posts; the text here is the full long-post text returned by the API, without the trailing image and quote links. Each carries one image, not copied here. At the same read the quoted post had 80 likes, 11 reposts, 3 replies and 34,896 views.
ENGAGEMENT
- likes53
- reposts5
- replies9
- quote1
- bookmarks8
- views19,120
AS RETURNED BY THE X API · FETCHED 2026-11-11 06:25 UTC
WHAT IT SAYS
Wall St Engine reports that SoftBank booked a $7 billion quarterly loss, including a $3.7 billion write-off on power equipment it had paid for upfront for its US data centres after changing its purchase plans. It says SoftBank shares fell 10% in Tokyo, describes the Ohio project as a 10 GW data centre on its own 9.2 GW gas plant, and quotes the CFO saying there are no plans to shrink it.
CONTEXT
CNBC confirms the net loss of 1.12 trillion yen (about $7 billion) for the quarter to 30 September and a 597.2 billion yen ($3.7 billion) loss from changes in procurement plans for power generation equipment for US AI data centres. SoftBank said it had paid in advance to secure equipment amid feared shortages and long lead times, and that cumulative payments for such equipment reached $9.48 billion by the end of September. CNBC also reports SoftBank shares closed 13.9% higher on the day of the results; I could not confirm the 10% fall the post describes, which may refer to a later session.
The US Department of Energy's March 2026 fact sheet says SoftBank and SB Energy plan 10 GW of new generation, including at least 9.2 GW of natural gas, to power 10 GW of data centres at the former Portsmouth Gaseous Diffusion Plant in Pike County, Ohio, plus $4.2 billion of new transmission with AEP Ohio paid for by SB Energy.
WHAT IT MEANS FOR K
A costly change of plan on generators, not a cancelled project: the 9.2 GW of gas planned for Ohio is still on the books, but the write-off shows how tight and expensive the market for power equipment has become.
CLAIMS
- SoftBank shares fell 10% in Tokyo (Wall St Engine; not confirmed by my sources).
- SoftBank has no plans to make the Ohio project smaller (CFO, as reported in the post).
EVIDENCE
- A $3.7 billion loss from changed procurement plans for power generation equipment, out of $9.48 billion paid so far (CNBC).
- The Ohio plan is 10 GW of generation, at least 9.2 GW of it gas, for 10 GW of data centres (US DOE).
REASONING
- Harvested power only changes when plants are built or cancelled; a write-off on advance payments changes who pays, not how many megawatts are planned.
- If the procurement change later shrinks or delays the Ohio generation, the verdict would move towards decelerating; for now the evidence points to no change in planned capacity, so I rate it neutral.